Senior power-engineer playbook for planning and operations optimization problems. Use whenever Egret or PyPSA studies are infeasible, reserve-deficient, congested, too expensive, or heavily curtailed — including escalations from a tool skill's OPF, unit-commitment, or expansion run. Triggers on 'OPF

License 许可
MIT
最近更新
2026-11-09
Stars
★ 0
Forks
0

01 前言 Front Matter

name
operations-planning-mitigation
risk
low
source
https://github.com/Power-Agent/PowerSkills
license
MIT
version
1.0.0
category
electrical-engineering
description
Senior power-engineer playbook for planning and operations optimization problems. Use whenever Egret or PyPSA studies are infeasible, reserve-deficient, congested, too expensive, or heavily curtailed — including escalations from a tool skill's OPF, unit-commitment, or expansion run. Triggers on 'OPF
imported_at
2026-09-20
source_path
powerskills-engineering/skills/operations-planning-mitigation/SKILL.md
source_repository
Power-Agent/PowerSkills
disable-model-invocation
false

03 SKILL.md 正文

Operations and planning mitigation

Start with the failed or unsatisfactory optimization result and the constraint set that caused it.

Preferred action order

  1. Fix data quality first: ramps, minimum output, up or down times, reserve requirements, network limits, and time-series assumptions.
  2. Solve a simpler screening case before a larger one: DC before AC, dispatch before unit commitment, operations before expansion.
  3. Add flexibility: storage, demand response, fast-start units, or revised reserve products.
  4. Relieve congestion with topology, transmission expansion, or better siting.
  5. Relax constraints or add slack variables only with explicit penalties and a clear explanation.

Working rules

  • Do not call a system infeasible before checking data consistency.
  • Separate economic congestion from physical AC infeasibility.
  • Validate promising fixes in an AC tool when voltage or reactive limits matter.

Deliver

  • The main binding constraints or infeasibility cause.
  • The best near-term operational fix.
  • The longer-term planning measure if the issue persists.