AGENT SKILL

renewable-resource-assessment

Assessing wind, solar, and hydro resources — measurement, modeling, uncertainty, and bankable energy-yield estimates.

License 许可
MIT
所属仓库
TanNhatCMS/jarvis
最近更新
2026-11-07
Stars
★ 0
Forks
1

01 前言 Front Matter

name
renewable-resource-assessment
category
scientific
description
Assessing wind, solar, and hydro resources — measurement, modeling, uncertainty, and bankable energy-yield estimates.

03 SKILL.md 正文

Overview

A renewable energy project lives or dies on the resource assessment: how much wind, sun, or water the site actually gets. This skill covers measurement campaigns (met masts, lidar, pyranometers), long-term correction with reanalysis (MCP), energy-yield modeling, and the uncertainty accounting that makes a yield estimate bankable.

When to use

  • Siting a wind or solar farm: screening sites and designing the measurement campaign
  • Converting a year of site data into a long-term (P50/P90) energy-yield estimate
  • Reviewing a resource assessment report for financing or acquisition
  • Estimating rooftop or distributed solar potential for a region
  • Assessing hydro resource variability and climate-change exposure

Core concepts

  • Wind: power ∝ v³ — small wind-speed errors become large energy errors; the Weibull distribution describes the speed frequency; shear (power law or log law) extrapolates mast height to hub height; turbulence intensity affects loads and production.

  • Solar: GHI (global horizontal), DNI (direct normal), DHI (diffuse); plane-of-array irradiance via transposition models; temperature derates PV output (~−0.35%/°C for silicon); soiling and shading are site-specific losses.

  • MCP (measure–correlate–predict): correlate short site measurements with long-term reference data (ERA5, MERRA-2) to estimate the long-term climate — the standard fix for interannual variability.

  • P50/P90: P50 is the median expected yield; P90 the conservative value exceeded 90% of the time — lenders size debt on P90; the P50–P90 gap measures total uncertainty.

  • Loss stack: availability, wake effects, electrical losses, soiling, curtailment, degradation — each small, together 10–20%; itemize rather than applying a single fudge factor.

  • Hydro: flow-duration curves from gauged records; firm vs secondary energy; sedimentation reduces storage; climate shifts alter both means and extremes.

  • Shear extrapolation risk: the power-law/log-law extrapolation from measurement height to hub height is a leading uncertainty source — measure as close to hub height as possible; lidar makes this cheap now.

  • Interannual variability vs climate change: 10–20 years of reference data captures variability; the climate-change signal in wind/solar resources is smaller but non-zero — check trends in the reference period before assuming stationarity.

  • Curtailment and grid constraints: the resource at the site is not the energy delivered — grid capacity, curtailment risk, and offtake terms belong in the yield assessment, not just the financial model.

Practical workflow

1. Measure the resource

  1. Wind: met mast or lidar at/near hub height, ≥12 months; calibrate anemometers; measure shear with multiple heights and direction with vanes.
  2. Solar: secondary-standard pyranometers (GHI + DHI) or reference cells, cleaned and calibrated; ≥12 months; log soiling with a paired clean/dirty sensor if dust is suspected.
  3. Document everything: sensor models, calibration certificates, heights, boom orientation, data recovery rate (>90% target).

2. Build the long-term estimate

  1. Select reference data (ERA5/MERRA-2 nodes, nearby long-term stations); validate correlation with concurrent site data (R², bias by direction/season).
  2. Apply MCP to synthesize a long-term (10–30 year) site time series; check that the reference period is climatologically representative.
  3. For wind, fit the long-term speed distribution and compute gross energy from the turbine power curve; for solar, transpose to plane-of-array and apply the temperature model.

3. Model energy yield and losses

  1. Wind: wake modeling (analytical or CFD-lite), availability (typically 97–98%), electrical losses, curtailment, icing if relevant.
  2. Solar: shading analysis, inverter clipping, mismatch, soiling, degradation (~0.5%/yr), availability.
  3. Present gross → net with each loss itemized; never bury losses in a single "derate."

4. Quantify uncertainty (the bankable part)

  1. List uncertainty components: measurement, MCP/reference, interannual variability, model/wake, losses — combine in quadrature (root-sum-square) with stated distributions.
  2. Report P50, P75, P90 (and P99 for stress tests); show which components dominate — that tells you what extra measurement would buy.
  3. Sensitivity-test key assumptions (shear exponent, soiling rate, degradation) — lenders will ask.

5. Audit a resource assessment report

  1. Check the measurement: duration (≥12 months?), heights, calibration certificates, data recovery rate — no measurement, no bankability.
  2. Check the MCP: reference dataset choice, correlation quality (R², directional/seasonal bias), reference-period representativeness.
  3. Check the uncertainty: itemized components combined properly, P90 derived not guessed, and loss stack itemized rather than lumped — then verify the P50 against independent data if any exists.

6. Quick-reference checklist

  • [ ] ≥12 months of site measurement at/near hub height (wind) or with calibrated pyranometers (solar)
  • [ ] Sensor calibrations current with certificates on file
  • [ ] Data recovery rate >90% with gaps documented
  • [ ] MCP performed against a validated long-term reference
  • [ ] Shear extrapolation minimized (measure high; lidar preferred)
  • [ ] Loss stack itemized (wakes, availability, electrical, soiling, curtailment, degradation)
  • [ ] Uncertainty components combined properly; P50/P90/P99 reported
  • [ ] Key assumptions sensitivity-tested (shear, soiling, degradation)

Common pitfalls

  • One windy year extrapolated forever: interannual variability is ±10% or more — MCP correction is mandatory, not optional.
  • v³ amplification: a 5% wind-speed bias is a ~15% energy bias — calibrate anemometers and scrutinize shear extrapolation.
  • Ignoring wakes and blockage: gross turbine yield ≠ farm yield; array effects cost 5–15%.
  • Soiling and shading hand-waving: in dusty or built environments these dominate uncertainty — measure, don't assume.
  • Degradation optimism: PV warranties promise ≤0.5%/yr; actuals vary — use measured fleet data where available.
  • Climate non-stationarity: 30-year historical normals may misstate the next 30 years for hydro and, increasingly, wind/solar regimes — check trends.
  • Vendor power curves as truth: manufacturer power curves are measured under ideal conditions — apply realistic turbulence, shear, and availability derates; validate against operational fleet data.
  • Soiling assumed zero: in arid and agricultural regions soiling losses of 5–20% are normal — a zero-soiling assumption needs site-specific justification, not optimism.

04 同仓库更多 Skills

TanNhatCMS
TanNhatCMS/jarvis

web-scrape

Turn web pages into LLM-ready markdown via the Firecrawl API (renders JS, anti-bot handling). Use when browser_open/fetch fails on JS-heavy pages, or when you need clean markdown/structured extraction from a site. Requires FIRECRAWL_API_KEY.

★ 0
TanNhatCMS
TanNhatCMS/jarvis

design-taste-frontend

tasteskill v2, the anti-slop frontend skill. Art direction for websites, distilled from a study of 247 curated gallery sites (One Page Love, Awwwards Sites of the Day). Deals researched directions (idea, composition, type, palette, photographs, section blueprints) from a library, enforces a strict no-slop house style with a real-browser inspector, and runs a look-and-fix loop on screenshots. Use this whenever you build, design, redesign, restyle, polish or review a landing page, marketing site, portfolio, product page, one-pager, hero or any public-facing web page, in any stack (HTML/CSS, React, Next.js, Vue, Svelte, Astro, Tailwind) — also when the user says a page looks generic, templated, "AI-made", sloppy, or asks to make it look designed, premium, award-level or less like every other site. Not for dashboards or app screens.

★ 0
TanNhatCMS
TanNhatCMS/jarvis

test-driven-development

Use when implementing any feature or bugfix, before writing implementation code

★ 0
TanNhatCMS
TanNhatCMS/jarvis

systematic-debugging

Use when encountering any bug, test failure, or unexpected behavior, before proposing fixes

★ 0
TanNhatCMS
TanNhatCMS/jarvis

requesting-code-review

Use when completing tasks, implementing major features, or before merging to verify work meets requirements

★ 0
TanNhatCMS
TanNhatCMS/jarvis

brainstorming

You MUST use this before any creative work - creating features, building components, adding functionality, modifying behavior, or planning anything new, in software or out of it (a talk, a business, a renovation).

★ 0