Use for day-ahead or multi-period unit commitment problems, including thermal on/off schedules, dispatch, startup/shutdown logic, minimum up/down time, ramping, spinning reserve deliverability, renewable curtailment, operating-cost accounting, and independent feasibility checks for power-system operations schedules.

License 许可
Apache-2.0
最近更新
2026-11-14
Stars
★ 0
Forks
1

01 前言 Front Matter

name
unit-commitment-operating-rules
description
Use for day-ahead or multi-period unit commitment problems, including thermal on/off schedules, dispatch, startup/shutdown logic, minimum up/down time, ramping, spinning reserve deliverability, renewable curtailment, operating-cost accounting, and independent feasibility checks for power-system operations schedules.

03 SKILL.md 正文

Unit Commitment Operating Rules

Use this skill when a task asks for a day-ahead or multi-period unit commitment schedule with generators, load, reserves, operating constraints, and cost tradeoffs.

This is a reusable UC operating guide. It gives formulation and validation patterns, not a complete task-specific mathematical model.

UC In One Paragraph

Unit commitment decides which generators are online over time, when they start or stop, how much they produce, and how much reserve they can physically provide. It is harder than hourly economic dispatch because startup/shutdown decisions, ramping, minimum up/down time, reserve deliverability, initial conditions, and cost curves couple one period to the next.

Keep These Concepts Separate

For each thermal unit g and period t:

u[g, t]      # commitment/on status, binary
start[g, t]  # startup transition, binary
stop[g, t]   # shutdown transition, binary
p[g, t]      # production variable: know whether actual MW or above-minimum MW
r[g, t]      # scheduled reserve

Reports often require actual MW output. Many UC models internally use output above minimum:

actual_output = pmin[g] * u[g, t] + p_above_min[g, t]
p_above_min = actual_output - pmin[g] * u[g, t]

Do not mix these conventions in ramping, reserve, cost, or reporting.

Core Feasibility Checks

Before reporting a schedule, independently verify:

  • every resource appears exactly once and all time-series have length T;
  • commitment, startup, and shutdown are binary;
  • offline thermal units have zero production and zero reserve;
  • online thermal units respect min/max output;
  • must-run units are online when required;
  • startup/shutdown indicators match commitment transitions;
  • demand balance holds in every period;
  • renewable output stays within period-specific bounds;
  • scheduled reserve meets the system requirement;
  • reserve is deliverable under headroom, startup/shutdown capability, and ramp limits;
  • minimum up/down time and initial conditions are respected;
  • cost and summary fields are recomputed from arrays.

Transition Logic

Link startup/shutdown to commitment and the initial state:

prev_u = initial_on[g] if t == 0 else u[g, t - 1]
u[g, t] - prev_u == start[g, t] - stop[g, t]
start[g, t] + stop[g, t] <= 1

Equivalent validation pattern:

prev_on = initial_on[g]
for t in range(T):
    assert start[g, t] == int(u[g, t] == 1 and prev_on == 0)
    assert stop[g, t] == int(u[g, t] == 0 and prev_on == 1)
    prev_on = u[g, t]

Capacity And Offline Zeroes

For actual-MW production:

pmin[g] * u[g, t] <= production[g, t] <= pmax[g] * u[g, t]
0 <= reserve[g, t]

For above-minimum production:

cap = pmax[g] - pmin[g]
0 <= p_above_min[g, t] <= cap * u[g, t]
0 <= reserve[g, t]

If u[g, t] == 0, both production and reserve must be zero.

Demand, Renewables, And System Reserve

Use the task's system/zone/network convention. For a single-zone system:

thermal_gen = sum(actual_thermal[g, t] for g in thermal_units)
renew_gen = sum(renewable_output[r, t] for r in renewable_units)
assert abs(thermal_gen + renew_gen - demand[t]) <= tol
assert sum(reserve[g, t] for g in thermal_units) >= reserve_requirement[t] - tol

Renewables:

renewable_min[r, t] <= renewable_output[r, t] <= renewable_max[r, t]

If min equals max, output is fixed. If curtailment is allowed, output may be below max. Do not count renewable headroom as spinning reserve unless the prompt explicitly allows it.

Reserve Deliverability

Reserve is not just unused nameplate capacity. Production and reserve compete for the same physical capability, and reserve must be deployable.

Headroom-only checks are too weak:

# Not enough by itself:
reserve[g, t] <= pmax[g] - production[g, t]
reserve[g, t] <= ramp_up[g]

Use joint production-plus-reserve checks. With actual-MW production:

production[g, t] + reserve[g, t] <= pmax[g] * u[g, t]

With above-minimum production:

p_above_min[g, t] + reserve[g, t] <= (pmax[g] - pmin[g]) * u[g, t]

Startup capability can tighten the startup period. If startup_limit is maximum total output during startup:

if start[g, t] == 1:
    production[g, t] + reserve[g, t] <= startup_limit[g]

A linear above-minimum pattern is:

startup_reduction = max(pmax[g] - startup_limit[g], 0.0)
p_above_min[g, t] + reserve[g, t] <= (
    (pmax[g] - pmin[g]) * u[g, t]
    - startup_reduction * start[g, t]
)

Apply analogous shutdown-period or pre-shutdown capability rules when the data and prompt require them.

Ramping

Use initial output/status for the first period. When reserve must be deliverable, ramp-up usually applies to production plus reserve:

previous = initial_above_min[g] if t == 0 else p_above_min[g, t - 1]
p_above_min[g, t] + reserve[g, t] - previous <= ramp_up[g]
previous - p_above_min[g, t] <= ramp_down[g]

If your model uses actual production, convert consistently before applying above-minimum ramp checks. Recheck ramping after any dispatch or repair step.

Minimum Up/Down Time

Minimum up/down constraints are time-window constraints triggered by starts/stops. Validation pattern:

if start[g, t] == 1:
    for tau in range(t, min(T, t + min_up[g])):
        assert u[g, tau] == 1

if stop[g, t] == 1:
    for tau in range(t, min(T, t + min_down[g])):
        assert u[g, tau] == 0

Account for pre-horizon time already on/off. Follow the prompt on whether post-horizon obligations are enforced.

Startup Costs

Startup cost may depend on prior offline duration. A common tier rule is largest lag not exceeding prior offline duration:

def choose_startup_cost(tiers, offline_duration):
    tiers = sorted(tiers, key=lambda z: z["lag"])
    chosen = tiers[0]
    for tier in tiers:
        if tier["lag"] <= offline_duration:
            chosen = tier
        else:
            break
    return chosen["cost"]

Update offline duration from initial status and the commitment trajectory. Be careful: duration should describe time offline before the startup period.

Production Costs

Use only cost components present in the data or required by the prompt. Do not invent no-load, reserve, curtailment, shutdown, or ramping costs.

For total-cost breakpoints:

def total_cost_from_curve(points, output_mw):
    pts = sorted((p["mw"], p["cost"]) for p in points)
    if output_mw <= pts[0][0]:
        return pts[0][1]
    if output_mw >= pts[-1][0]:
        return pts[-1][1]
    for (x0, y0), (x1, y1) in zip(pts, pts[1:]):
        if x0 <= output_mw <= x1:
            return y0 + (output_mw - x0) * (y1 - y0) / (x1 - x0)
    raise ValueError("output outside curve")

If the first point is at minimum output, its cost may represent online minimum-output cost. Do not add another fixed online cost unless the data says so.

Objective Semantics Audit (piecewise curves + double-count prevention)

If your schedule is feasible and your internal cost recomputation matches your report, but the objective still looks economically implausible (e.g., far higher than expected, wrong merit order, or dispatch that ignores cheap generation), audit the meaning of the production-cost data before changing feasibility constraints.

Perform this audit whenever costs are given as breakpoint tables such as piecewise_production:

  1. Determine the curve convention (do not assume). For each thermal generator, decide whether the cost field at breakpoints is:

    • total cost at output MW (most common in UC benchmarks), or
    • incremental segment cost (already a slope/cost for the segment), or
    • marginal cost / heat-rate-like data.
  2. Encode costs to match that convention.

    • If points are total cost, model cost using a convex-combination / SOS2 formulation over breakpoints, or derive segment slopes as Δcost/Δmw between consecutive points and apply them only to segment quantities.
    • If points are incremental/marginal, do not re-integrate them into another “total cost” curve and do not treat the values as total cost at MW.
  3. Prevent double-counting at minimum output. If you model actual MW production and also enforce production >= pmin * u, then:

    • do not separately add a fixed “no-load” or “min-output” cost unless it is explicitly provided and not already embedded in the first breakpoint’s cost;
    • do not add the first breakpoint cost every period as a separate term if your piecewise interpolation already returns total cost at that output.
  4. Spot-check unit economics numerically (cheap, high-value test). For a few generators:

    • compute cost at pmin and pmax from your model’s cost expression;
    • compare against the interpolation implied by the raw points;
    • compute implied $/MWh slopes between adjacent breakpoints and confirm they are nonnegative and roughly consistent with unit type expectations.
  5. Fallback verification: single-period dispatch sanity check. Fix commitments for one hour (or pick a representative hour) and solve a continuous dispatch/reserve subproblem using the same cost model. If the resulting dispatch violates basic merit-order intuition (expensive units loaded while cheaper units are available), revisit step (1)–(3) before blaming ramping/reserve/min-up constraints.

This audit is diagnostic and objective-encoding focused: it should not weaken feasibility families (startup/shutdown, minimum up/down, ramping, reserve deliverability).

Implementation Workflow

  1. Parse and normalize resource/time arrays.
  2. Choose actual-output or above-minimum internal variables and stick to it.
  3. Include hard feasibility constraints before optimizing cost.
  4. Extract the solution into the report convention.
  5. Run independent validation on extracted arrays.
  6. Recompute costs and summaries from arrays.
  7. Write "pass" checks only after validation passes.

Common Pitfalls

  • Treating UC as independent hourly dispatch.
  • Counting reserve from offline units or renewable headroom.
  • Checking reserve headroom but forgetting startup or ramp deliverability.
  • Ignoring initial output in first-period ramping.
  • Ignoring initial on/off duration in minimum up/down constraints.
  • Trusting a repair LP that omits a constraint family.
  • Hard-coding "pass" fields before validation.