Use for day-ahead or multi-period unit commitment problems, including thermal on/off schedules, dispatch, startup/shutdown logic, minimum up/down time, ramping, spinning reserve deliverability, renewable curtailment, operating-cost accounting, and independent feasibility checks for power-system operations schedules.

License 许可
Apache-2.0
最近更新
2026-11-14
Stars
★ 0
Forks
1

01 前言 Front Matter

name
unit-commitment-operating-rules
description
Use for day-ahead or multi-period unit commitment problems, including thermal on/off schedules, dispatch, startup/shutdown logic, minimum up/down time, ramping, spinning reserve deliverability, renewable curtailment, operating-cost accounting, and independent feasibility checks for power-system operations schedules.

03 SKILL.md 正文

Unit Commitment Operating Rules

Use this skill when a task asks for a day-ahead or multi-period unit commitment schedule with generators, load, reserves, operating constraints, and cost tradeoffs.

This is a reusable UC operating guide. It gives formulation and validation patterns, not a complete task-specific mathematical model.

UC In One Paragraph

Unit commitment decides which generators are online over time, when they start or stop, how much they produce, and how much reserve they can physically provide. It is harder than hourly economic dispatch because startup/shutdown decisions, ramping, minimum up/down time, reserve deliverability, initial conditions, and cost curves couple one period to the next.

Keep These Concepts Separate

For each thermal unit g and period t:

u[g, t]      # commitment/on status, binary
start[g, t]  # startup transition, binary
stop[g, t]   # shutdown transition, binary
p[g, t]      # production variable: know whether actual MW or above-minimum MW
r[g, t]      # scheduled reserve

Reports often require actual MW output. Many UC models internally use output above minimum:

actual_output = pmin[g] * u[g, t] + p_above_min[g, t]
p_above_min = actual_output - pmin[g] * u[g, t]

Do not mix these conventions in ramping, reserve, cost, or reporting.

Mandatory Production-Representation Contract

Before adding any capacity, ramp, startup/shutdown, reserve, balance, or cost row, write down a one-line model contract declaring whether the continuous thermal production variable is actual MW or MW above minimum. Do not start coding those rows until this contract is fixed.

The safest default for formulations with startup/shutdown capability and ramp deliverability is often an above-minimum variable:

pbar[g, t] = actual_output[g, t] - pmin[g] * u[g, t]
cap[g] = pmax[g] - pmin[g]

Then the core rows have one consistent meaning:

0 <= pbar[g, t] <= cap[g] * u[g, t]

# headroom plus startup capability
pbar[g, t] + r[g, t] <= (
    cap[g] * u[g, t]
    - max(pmax[g] - startup_limit[g], 0.0) * start[g, t]
)

# pre-shutdown capability when stop[t+1] means the unit turns off next period
pbar[g, t] + r[g, t] <= (
    cap[g] * u[g, t]
    - max(pmax[g] - shutdown_limit[g], 0.0) * stop[g, t + 1]
)

prev_pbar = initial_on[g] * (initial_output[g] - pmin[g]) if t == 0 else pbar[g, t - 1]
pbar[g, t] + r[g, t] - prev_pbar <= ramp_up[g]
prev_pbar - pbar[g, t] <= ramp_down[g]

If you instead model actual MW P, derive the algebraically equivalent rows rather than copying the above-minimum equations verbatim. Since pbar = P - pmin*u, ramping becomes:

prev_P = initial_output[g] if t == 0 else P[g, t - 1]
prev_u = initial_on[g] if t == 0 else u[g, t - 1]

P[g, t] + r[g, t] - prev_P - pmin[g] * (u[g, t] - prev_u) <= ramp_up[g]
prev_P - P[g, t] - pmin[g] * (prev_u - u[g, t]) <= ramp_down[g]

The pmin * delta_u terms are essential at transitions. Using only P[t] + r[t] - P[t-1] <= ramp_up on actual MW incorrectly charges the minimum stable output as ramp movement during an off-to-on transition. Likewise, P[t-1] - P[t] <= ramp_down incorrectly charges minimum output again at shutdown.

For actual MW, the startup/headroom row is equivalently:

P[g, t] + r[g, t] <= (
    pmax[g] * u[g, t]
    - max(pmax[g] - startup_limit[g], 0.0) * start[g, t]
)

and demand balance uses actual MW directly. For above-minimum variables, demand balance must add the minimum-output term:

sum(pbar[g, t] + pmin[g] * u[g, t] for g in thermal_units) + renewable_generation[t] == demand[t]

Mandatory transition hand-case gate

Before solving the full horizon, evaluate the actual encoded row coefficients on at least these cases for a representative unit:

  1. steady online: u_prev=1, u=1;
  2. startup at minimum output: u_prev=0, u=1, P=pmin;
  3. shutdown from minimum output: u_prev=1, u=0, P_prev=pmin.

In case 2, minimum stable output must map to pbar=0; it must not consume pmin MW of ordinary ramp allowance solely because the unit changed commitment state. In case 3 the symmetric rule applies. If the hand case fails, the representation is mixed and the full model must not be solved or reported yet.

Keep the representation contract next to the implementation and reuse it in independent validation. Validation must not simply copy the same mixed-convention algebra from the optimization model.

Core Feasibility Checks

Before reporting a schedule, independently verify:

  • every resource appears exactly once and all time-series have length T;
  • commitment, startup, and shutdown are binary;
  • offline thermal units have zero production and zero reserve;
  • online thermal units respect min/max output;
  • must-run units are online when required;
  • startup/shutdown indicators match commitment transitions;
  • demand balance holds in every period;
  • renewable output stays within period-specific bounds;
  • scheduled reserve meets the system requirement;
  • reserve is deliverable under headroom, startup/shutdown capability, and ramp limits;
  • minimum up/down time and initial conditions are respected;
  • cost and summary fields are recomputed from arrays.

Transition Logic

Link startup/shutdown to commitment and the initial state:

prev_u = initial_on[g] if t == 0 else u[g, t - 1]
u[g, t] - prev_u == start[g, t] - stop[g, t]
start[g, t] + stop[g, t] <= 1

Equivalent validation pattern:

prev_on = initial_on[g]
for t in range(T):
    assert start[g, t] == int(u[g, t] == 1 and prev_on == 0)
    assert stop[g, t] == int(u[g, t] == 0 and prev_on == 1)
    prev_on = u[g, t]

Capacity And Offline Zeroes

For actual-MW production:

pmin[g] * u[g, t] <= production[g, t] <= pmax[g] * u[g, t]
0 <= reserve[g, t]

For above-minimum production:

cap = pmax[g] - pmin[g]
0 <= p_above_min[g, t] <= cap * u[g, t]
0 <= reserve[g, t]

If u[g, t] == 0, both production and reserve must be zero.

Demand, Renewables, And System Reserve

Use the task's system/zone/network convention. For a single-zone system:

thermal_gen = sum(actual_thermal[g, t] for g in thermal_units)
renew_gen = sum(renewable_output[r, t] for r in renewable_units)
assert abs(thermal_gen + renew_gen - demand[t]) <= tol
assert sum(reserve[g, t] for g in thermal_units) >= reserve_requirement[t] - tol

Renewables:

renewable_min[r, t] <= renewable_output[r, t] <= renewable_max[r, t]

If min equals max, output is fixed. If curtailment is allowed, output may be below max. Do not count renewable headroom as spinning reserve unless the prompt explicitly allows it.

Reserve Deliverability

Reserve is not just unused nameplate capacity. Production and reserve compete for the same physical capability, and reserve must be deployable.

Headroom-only checks are too weak:

# Not enough by itself:
reserve[g, t] <= pmax[g] - production[g, t]
reserve[g, t] <= ramp_up[g]

Use joint production-plus-reserve checks. With actual-MW production:

production[g, t] + reserve[g, t] <= pmax[g] * u[g, t]

With above-minimum production:

p_above_min[g, t] + reserve[g, t] <= (pmax[g] - pmin[g]) * u[g, t]

Startup capability can tighten the startup period. If startup_limit is maximum total output during startup:

if start[g, t] == 1:
    production[g, t] + reserve[g, t] <= startup_limit[g]

A linear above-minimum pattern is:

startup_reduction = max(pmax[g] - startup_limit[g], 0.0)
p_above_min[g, t] + reserve[g, t] <= (
    (pmax[g] - pmin[g]) * u[g, t]
    - startup_reduction * start[g, t]
)

Apply analogous shutdown-period or pre-shutdown capability rules when the data and prompt require them.

Ramping

Use initial output/status for the first period. When reserve must be deliverable, ramp-up usually applies to production plus reserve:

previous = initial_above_min[g] if t == 0 else p_above_min[g, t - 1]
p_above_min[g, t] + reserve[g, t] - previous <= ramp_up[g]
previous - p_above_min[g, t] <= ramp_down[g]

If your model uses actual production, use the exact conversion in the Mandatory Production-Representation Contract above; do not apply these above-minimum rows directly to actual MW. Recheck ramping after any dispatch or repair step.

Minimum Up/Down Time

Minimum up/down constraints are time-window constraints triggered by starts/stops. Validation pattern:

if start[g, t] == 1:
    for tau in range(t, min(T, t + min_up[g])):
        assert u[g, tau] == 1

if stop[g, t] == 1:
    for tau in range(t, min(T, t + min_down[g])):
        assert u[g, tau] == 0

Account for pre-horizon time already on/off. Follow the prompt on whether post-horizon obligations are enforced.

Startup Costs

Startup cost may depend on prior offline duration. A common tier rule is largest lag not exceeding prior offline duration:

def choose_startup_cost(tiers, offline_duration):
    tiers = sorted(tiers, key=lambda z: z["lag"])
    chosen = tiers[0]
    for tier in tiers:
        if tier["lag"] <= offline_duration:
            chosen = tier
        else:
            break
    return chosen["cost"]

Update offline duration from initial status and the commitment trajectory. Be careful: duration should describe time offline before the startup period.

Production Costs

Use only cost components present in the data or required by the prompt. Do not invent no-load, reserve, curtailment, shutdown, or ramping costs.

For total-cost breakpoints:

def total_cost_from_curve(points, output_mw):
    pts = sorted((p["mw"], p["cost"]) for p in points)
    if output_mw <= pts[0][0]:
        return pts[0][1]
    if output_mw >= pts[-1][0]:
        return pts[-1][1]
    for (x0, y0), (x1, y1) in zip(pts, pts[1:]):
        if x0 <= output_mw <= x1:
            return y0 + (output_mw - x0) * (y1 - y0) / (x1 - x0)
    raise ValueError("output outside curve")

If the first point is at minimum output, its cost may represent online minimum-output cost. Do not add another fixed online cost unless the data says so.

Implementation Workflow

  1. Parse and normalize resource/time arrays.
  2. Freeze the production representation contract and pass its transition hand-case gate.
  3. Include hard feasibility constraints before optimizing cost.
  4. Extract the solution into the report convention.
  5. Run independent validation on extracted arrays using the report/physical convention rather than blindly reusing model rows.
  6. Recompute costs and summaries from arrays.
  7. For an economical/objective-scored task, inspect starts/stops and run the independent objective-quality gate from the MILP workflow before claiming optimality.
  8. Write "pass" checks only after validation passes.

Common Pitfalls

  • Treating UC as independent hourly dispatch.
  • Counting reserve from offline units or renewable headroom.
  • Checking reserve headroom but forgetting startup or ramp deliverability.
  • Mixing actual MW and above-minimum MW in transition or ramp rows.
  • Charging pmin as ordinary ramp movement on startup or shutdown.
  • Ignoring initial output in first-period ramping.
  • Ignoring initial on/off duration in minimum up/down constraints.
  • Trusting a repair LP that omits a constraint family.
  • Trusting a zero MIP gap without auditing the encoded formulation and economic signature.
  • Hard-coding "pass" fields before validation.