Create and maintain numbered phase and implementation plans in `plans/` for the Prism repo. Every task carries acceptance criteria, an evidence-based approach, tests written first, a docs assessment, and the repo's chores built in (kernel/package placement, compat baselines, retirement sweeps, conformance suites, examples, staged docs, backlog handoff), so executing the plan leaves no debt. Use whenever asked to create, write, update, or maintain a plan, including a roadmap phase plan, implementation plan, task breakdown, or plan document. Executing plan tasks is the prism-execution skill.

License 许可
MIT
所属仓库
ashiqrniloy/prism
最近更新
2026-11-15
Stars
★ 0
Forks
0

01 前言 Front Matter

name
create-plan
description
Create and maintain numbered phase and implementation plans in `plans/` for the Prism repo. Every task carries acceptance criteria, an evidence-based approach, tests written first, a docs assessment, and the repo's chores built in (kernel/package placement, compat baselines, retirement sweeps, conformance suites, examples, staged docs, backlog handoff), so executing the plan leaves no debt. Use whenever asked to create, write, update, or maintain a plan, including a roadmap phase plan, implementation plan, task breakdown, or plan document. Executing plan tasks is the prism-execution skill.

02 资源文件 3

03 SKILL.md 正文

Create Plan

A plan turns one roadmap phase, or one self-contained change, into checkable tasks. A plan is good when an executor who follows it literally leaves no debt:

  • every moved export has its baseline regeneration
  • every retired name has its repo-wide sweep
  • every new surface has a test, an example, and docs
  • the tree is green after every task

Workflow

  1. Read the source.
    • Read the roadmap.md phase you are planning (Goal, Why, Scope, Done) and every Part 1–2 section it touches, plus PRODUCT.md.
    • The plan implements the roadmap; it does not redesign it.
    • If code reality conflicts with the roadmap, record the conflict as a finding in the review task and stop. Do not improvise around it.
  2. Load the references. Always read both:
    • references/prism.md: placement rules, the phase review task, the task probes, chore checklists by change type, and tooling assumptions.
    • references/prism-wiki.md: where docs go (kernel /docs pages, package READMEs, CHANGELOG.md), and page structures.
  3. Survey the code with graft before writing approaches.
    • graft ask "<scope bullet>" --source to find the relevant code.
    • graft callers <symbol> --depth all for every symbol a task renames, moves, or deletes.
    • Cite file:line in each approach.
    • Use the find-docs skill for third-party library or CLI APIs.
  4. Name the file. Use the next three-digit prefix in plans/, as NNN-Phase-N-<Title>.md for roadmap phases. Split an oversized phase into NNN-Phase-N-Part-A-<Title>.md / Part-B with an explicit dependency line.
  5. Draft the tasks.
    • Start with the phase review task whenever references/prism.md §2 requires one.
    • Run every task through the probes in references/prism.md §3. Each probe answer becomes an acceptance criterion, a listed file, or a test, or an explicit n/a — <reason>.
    • Order the tasks so each one leaves the tree green.
  6. Index the plan. Add a row to plans/README.md with status planned. The docs test fails for an unindexed numbered plan.
  7. Run the self-check below before presenting the plan.

Required plan structure

# <Plan Title>

## Objectives
- <Objective>

## Expected Outcome
- <Observable deliverable or system state after completion>

<One paragraph: which roadmap phase this implements, whether a review task is included (or why not), what does not ship (version bump, publish, /docs), and anything unusual about this plan.>

## Tasks

- [ ] Task N: <title>
  - Acceptance Criteria:
    - Functional: <behavior, including fail-closed cases and the retirement sweep>
    - Performance: <latency/resource/load-cost expectation or explicit non-regression>
    - Code Quality: <placement, typing, no aliases, no speculative abstraction>
    - Security: <trust boundary, secrets, capabilities, what fails closed>
  - Approach:
    - Documentation Reviewed:
      - <roadmap sections, docs pages, code at file:line, third-party docs with versions>
    - Options Considered:
      - <option — why rejected>
    - Chosen Approach:
      - <why this fits>
    - API Notes and Examples:
      ```ts
      <minimal API shape or command>
      ```
    - Files to Create/Edit:
      - `<path>`: <change>   (complete list; mark tentative entries and say why)
    - References:
      - <code paths, decisions, prior plans>
  - Test Cases to Write:
    - <test name>: <what it proves; which break makes it fail>
  - Documentation/Wiki Assessment:
    - Public API or behavior impacted: <yes/no and why>
    - Docs pages to create/edit:
      - `<path>`: <change, or `none` with reason>
    - `docs/index.md` update: <yes/no>
    - Documentation structure reference: `.agents/skills/create-plan/references/prism-wiki.md`
  - Notes (executed <date>):   ← written by the executor, not while drafting

## Verification (whole plan)
- <runnable commands, in order>

## Compromises Made
- To be filled after tasks are completed and tests pass.

## Further Actions
- To be filled after task completion with improvements, rationale, and priority.

Task writing rules

  • Every task is independently checkable (- [ ] / - [x]) and has all four criteria categories.
  • The approach is mandatory and evidence-based. An option without a rejection reason is not an option.
  • Write test cases before implementation. Derive them from the criteria, name each test, and say which break makes it fail.
  • Every task leaves bun run typecheck and the task's suites green. A rename updates all of its callers in the same task. Never write "red until Task N": plan 142 left the root typecheck red across four tasks because callers were deferred.
  • A task that moves, renames, or removes a public export must plan the baseline regeneration in that same task:
    • Name bun scripts/release.mjs gate --update-baseline and the scripts/compat-baseline/ files it rewrites.
    • Require the post-regeneration diff in the task note, with removals attributed to this plan or inherited.
    • This rule exists because plan 083 skipped the regeneration, leaving release:gate red for every later plan, and plan 142 missed assembleAppAgent's return type in the prism-code baseline.
  • A task that changes an error contract (code, class, or refusal shape) or retires a name must put the name in the standing sweep. bun scripts/retired-names.mjs --generate picks up removed exports, subpaths, packages, ERR_* codes, and prism flags from the compat baselines; a removed tool goes in scripts/retired-tool-names.json; a name that stays an ordinary word goes in vocabulary with a reason. scripts/retired-names.test.mjs (no_retired_name_in_live_tree, in bun run test) then fails on any live use under src/ packages/ apps/ scripts/ examples/ docs/. It skips dist/, plans/, docs/history/, docs/_evidence/, migration guides, tests, and sentences that state the removal. Plan 080 left retired errors asserted in a Postgres test and a script fixture.
  • A new opt-in cost or durability knob states its sizing trade-off (extra writes, requests, or model calls per unit of work, plus the default that avoids them) in the owning docs page or README, not only in the plan.
  • Every task has a Documentation/Wiki Assessment per references/prism-wiki.md.
  • Scope discipline. Implement the roadmap phase. Anything beyond it goes to Further Actions, not into a task.
  • Do not fill Compromises Made or Further Actions while drafting unless a constraint is already known. Do not write plans/backlog.md while drafting.

Self-check before presenting

  • [ ] The review task is present, or the header says why the plan changes no contract.
  • [ ] Every task answers the references/prism.md §3 probes: placement, mechanism, fail-closed, secrets, load cost, retirement, public surface, callers, proof, docs, enforcement rows, reference host impact, cost knobs.
  • [ ] No task leaves the tree red; every rename updates its callers in the same task.
  • [ ] Every export move plans a baseline regeneration; every retired name or error plans a sweep.
  • [ ] Every new package, example, or docs page plans its enforcement-row updates (references/prism.md §3 probe 11).
  • [ ] ## Verification (whole plan) lists runnable commands.
  • [ ] The plan row exists in plans/README.md.

Plan end (executor runs this; plans leave room for it)

After the whole-plan verification passes, fill Compromises Made and Further Actions, then hand both off to plans/backlog.md:

  • Create the backlog file only if there are items. Copy items; do not remove them from the plan.
  • If an entry with the same source plan, section, and title already exists, update it in place instead of adding a duplicate.
  • After writing, add Recorded in plans/backlog.md. to each section.

Entry shape:

  • ## <title> (for a compromise: the follow-up that revisits or undoes it)
  • - Section: Compromises Made | Further Actions
  • - Priority: P1 | P2 | P3 | P4 (P1 highest; assign one if missing and record it in the plan too)
  • - Source: plans/<plan-file>.md
  • Compromises: - Compromise: what was done, and - Implications: what it costs or risks
  • Further Actions: - What: the task, and - Why: why it is needed

A plan made obsolete by a roadmap change is closed, not deleted:

  • Mark its unexecuted tasks Dropped by plan NNN (<date>): <reason>.
  • Set its plans/README.md status to superseded by NNN or closed at Task N.
  • Remove its backlog entries only when they track the withdrawn direction, and name the removed titles in the closing plan's task note.