estimate
Three-point (PERT-style) estimates per step. The point isn't a date; it's calibrating uncertainty.
Mode: deterministic — same inputs, same output. Follow the steps and the output shape exactly; compute with the named script or tool, never by estimate; add nothing the shape does not ask for.
When to use
- A work breakdown exists and stakeholders need a sense of when.
- The user says "how long will this take?".
Inputs
- A work breakdown (required) — output of
polymath-planning:work-breakdownor any list of steps. None given: stop and ask for one (or runwork-breakdownfirst); never estimate an undecomposed goal. - O / E / P hours per step (required) — from the people doing the work. Unattended run (workflow step, subagent): draft them yourself, append
?to every drafted number, and title the output DRAFT — numbers not confirmed by the team. - Which steps are on the critical path (optional, default: all — sequential).
- Team focus hours per working day (optional, default 5; never assume 8).
Procedure
-
For each step, collect three numbers in hours:
- Optimistic (~10th percentile): everything goes right.
- Expected (~50th): typical run.
- Pessimistic (~90th): known knowns go wrong.
-
Compute with the bundled script — never by hand. It applies per step
μ = (O + 4E + P) / 6andσ = (P − O) / 2.56(O and P are 10th/90th percentiles, so classic PERT's/6would understate σ), sums the critical-path means, root-sum-squares the critical-path σ, and reports the 80% intervalμ ± 1.28 σ_total:python3 "${POLYMATH_PLUGIN_ROOT:-${CLAUDE_PLUGIN_ROOT}}/skills/estimate/scripts/pert.py" \ --goal "<goal>" --focus-hours 5 <<'CSV' step,o,e,p,critical Write the migration,2,4,8,y Add the limiter middleware,1,2,8,y Update the runbook,1,1,2,n CSVExit 2 means bad input (e.g. O > E): fix the row, never the arithmetic.
-
Paste the script output verbatim. Do not re-round, re-order, or "correct" it.
-
Act on its flags: any step with
P / O > 3is poorly scoped — decompose it and re-run before anyone commits to the total. Steps that share a cause of delay (same unknown, same team) are correlated: say so, because the interval assumes independence and is too narrow for them. Summing all the O's and all the P's is not a confidence interval. -
Write the result to
docs/plans/<slug>-estimate.mdwhen a plan exists for it (same slug as the plan); otherwise return it inline.
Output
The script's block, verbatim, then one line of correlation notes:
Estimate: Rate-limit /login
Per-step (hours):
Step O E P Mean σ
1. Write the migration 2 4 8 4.3 2.3 ← P/O > 3, decompose
2. Add the limiter middleware 1 2 8 2.8 2.7 ← P/O > 3, decompose
3. Update the runbook 1 1 2 1.2 0.4 ← off critical path
Critical path mean: 7.2 h ≈ 1.4 working days at 5 focus h/day
80% interval: 2.6 .. 11.8 h (0.5 .. 2.4 days; σ_total = 3.6 h, independent steps — correlated risks widen it)
Decompose before committing: Write the migration, Add the limiter middleware
Correlated risks: steps 1–2 share the unknown "does the gateway expose client IP?" — treat 11.8 h as optimistic.
Quality bar
- Every number in the output came from the script; none was computed or adjusted in prose.
- Estimates in hours, not story points. Story points hide uncertainty rather than surface it.
- Any step with
P / O > 3is flagged for decomposition; don't silently commit to it. - Calendar conversion uses the team's actual focus hours per day (not 8).
- Drafted (unconfirmed) numbers carry
?and the DRAFT title — never presented as the team's estimate.
04 同仓库更多 Skills
runbook
Write or refresh an operational runbook for an alert/symptom; structured as TL;DR + Pre-checks + Steps + Verification + Rollback + Escalation.
rfc
Draft a lightweight design RFC to docs/rfcs/<slug>.md; Summary, Motivation, Detailed design, Drawbacks, Alternatives, Unresolved questions. A proposal to debate, not a recorded decision (adr).
editorial-pass
Review and tighten prose in a Markdown artifact for a target tone (terse, formal, friendly) without dropping information; preserve quotations and load-bearing constraints.
architecture-review-facilitation
Run an architecture review as a process — entry criteria, reviewer checklist, decision log, and follow-up actions — pairing the design artifact with a red-team pass.
architecture-doc
Write a C4-style architecture document; System Context + Containers (+ Components when interesting) with mermaid diagrams. Describes structure, not a decision (adr) or proposal (rfc).
adr
Write an Architecture Decision Record (Michael Nygard format) to docs/adrs/NNNN-<slug>.md; frontmatter validated by the ADR artifact schema. Records a made decision, not a proposal to debate (rfc).