Sprint Status Workflow

Goal

Produce a concise, accurate sprint status report covering completed work, work in progress, blockers, and burn-down trajectory. Surface risks the team needs to act on now.


Step 1: Load Sprint Context

Read _superml/config.yml for sprint information.

Ask if not present:

  1. Sprint name / number?
  2. Sprint start date and end date?
  3. Total story points committed?

Step 2: Story Status Sweep

For each story in the current sprint, classify:

Status Description
✅ Done Implemented, reviewed, and meets ACs
🔄 In Progress Currently being worked on
⚠️ Blocked Cannot proceed — dependency or external blocker
⏳ Not Started Committed but not yet picked up

Collect:

  • Points done: {X} of {total} committed
  • Days remaining in sprint: {N}
  • Projected completion rate (points/day) vs. required rate

Step 3: Blocker Analysis

For each blocked story:

  • What is the blocker? (technical, dependency, access, decision needed)
  • Who needs to act to unblock?
  • How many story points are blocked?
  • What is the risk to sprint goal?

Step 4: Risk Assessment

Evaluate:

  • Is the sprint on track? (current velocity vs. needed velocity)
  • Is the sprint goal at risk?
  • Should any stories be descoped? Which ones are lowest priority?
  • Are any blockers escalation-worthy?

Step 5: Output

Report format:

Sprint: {name}  |  Day {N} of {total}  |  {X}/{total} pts done

✅ Done ({X} pts)
  - S-001: [Story title]
  - S-003: [Story title]

🔄 In Progress ({Y} pts)
  - S-002: [Story title] — {owner}

⚠️ Blocked ({Z} pts)
  - S-004: [Story title] — BLOCKER: {description} — Needs: {owner}

⏳ Not Started ({W} pts)
  - S-005: [Story title]

📊 Burn-down: {X}/{total} pts done, {days} days left
   Needed: {required_rate} pts/day  |  Current: {actual_rate} pts/day
   Status: {ON TRACK / AT RISK / OFF TRACK}

🚨 Risks:
  1. {risk description} — Recommended action: {action}

Save to {docsPath}/planning/sprint-status-{sprint}.md.