Retrospective Workflow
Goal
Run a structured, blame-free retrospective that produces clear, owned action items the team will actually execute. Not a venting session — a problem-solving session.
Step 1: Set the Stage
Establish ground rules:
- This is a blame-free session — we discuss systems and processes, not people
- Everything said here stays in the retro doc unless explicitly agreed otherwise
- We focus on actionable improvements, not just complaints
Ask:
- Sprint name / number?
- Who is participating? (list personas or team members)
- Any topics to explicitly put on the table?
Step 2: What Went Well?
Go around — each participant shares at least one positive:
- Something that worked better than expected
- A process or decision that paid off
- A collaboration or communication win
Capture all positives. Group related ones into themes.
Step 3: What to Improve?
Go around — each participant shares their main friction point:
- Something that slowed the team down
- A process that caused confusion or rework
- A missing artifact, decision, or communication
Capture all points. Group into themes. Vote (or let the Team Lead choose) the top 2 to dig into.
Step 4: Root Cause — Five Whys
For each top-2 improvement area, run a five-whys:
Problem: [description]
Why 1: [answer]
Why 2: [answer]
Why 3: [answer]
Why 4: [answer]
Root cause: [answer]
Stop when you reach a root cause the team can actually address.
Step 5: Action Items
For each root cause, define ONE action item:
| Action | Owner | Due Date | Success Criterion |
|---|---|---|---|
| ... | ... | ... | ... |
Rules:
- One owner per action (not "the team")
- Due date is no later than end of next sprint
- Success criterion is observable — you can verify it happened
Step 6: Appreciation Round
Each participant thanks one other participant for something specific this sprint.
Step 7: Output
Save to {docsPath}/planning/retro-{sprint}.md with:
- Sprint metadata
- Went well (grouped themes)
- To improve (grouped themes)
- Root cause analysis for top 2
- Action items table
- Appreciation notes
04 同仓库更多 Skills
jira-sync
Bulk sync all epics and stories from the local backlog to JIRA. Use when the user says 'sync to JIRA', 'push everything to JIRA', or 'create all JIRA tickets'.
jira-create-story
Create a single story ticket in JIRA from a local story file. Use when the user says 'create this story in JIRA' or 'push story to JIRA'.
jira-create-epic
Create an epic in JIRA from a planning artifact. Use when the user says 'create this epic in JIRA' or 'push epic to JIRA'.
jira-connect
Set up and verify JIRA integration. Use when the user says 'connect to JIRA', 'set up JIRA', or 'configure JIRA'.
jira-conflict-detect
Check if a story is already being worked on by another team member. Use before starting any story implementation.
gitlab-create-mr
Create a GitLab Merge Request for the current story branch. Use when the user says 'create an MR', 'open a merge request', or 'ready for review' in a GitLab project.