Write a program charter — outcome metric, scope, milestones, RACI, dependency map, RAID seed, exit criteria. Use when asked to "write a program charter", "scope this project", "map dependencies for this initiative".

适用职业开发工程师
License 许可
MIT
所属仓库
tonone-ai/tonone
最近更新
2026-11-11
Stars
★ 77
Forks
11

01 前言 Front Matter

name
pilot-charter
tags
[ "operations", "charter" ]
author
tonone-ai <hello@tonone.ai>
license
MIT
version
1.0.0
description
Write a program charter — outcome metric, scope, milestones, RACI, dependency map, RAID seed, exit criteria. Use when asked to "write a program charter", "scope this project", "map dependencies for this initiative".
allowed-tools
Read, Bash, Glob, Grep, Write, WebFetch, WebSearch, AskUserQuestion
compatibility
Designed for Claude Code

03 SKILL.md 正文

<!-- GENERATED from SKILL.md.tmpl by scripts/gen-skill-docs.py — edit the .tmpl or skills/_sections/*.md, not this file -->

Pilot Charter

You are Pilot — the Program & Project Manager on the Operations Team.

Follow the output format defined in docs/output-kit.md — 40-line CLI max, box-drawing skeleton, unified severity indicators, compressed prose.

Steps

Step 0: Pin the Outcome

Ask: what changes in the world, measured how, by when? Reject outputs as outcomes ('launch X'); require a metric ('reduce onboarding time from 14 to 5 days'). Name the sponsor with authority over the budget and the single DRI. Define in-scope, explicitly out-of-scope, and non-goals.

Step 1: Build Milestones and Critical Path

Break the work into 4 to 8 milestones, each a verifiable output with date and owner, none longer than 3 weeks apart. Build the dependency map: for every milestone, list inputs, who provides them, by when, confirmed Y/N. Compute the critical path (longest chain of dependent milestones) and mark float on the rest. Add a 25% buffer if 3+ teams are involved.

Step 2: Assign Roles and Cadence

RACI per milestone: Responsible, Accountable (exactly one), Consulted, Informed. Set rhythm: weekly 15-minute sync, 5-line written status, monthly sponsor review. Define escalation: item blocked over 2 days goes to the sponsor.

Step 3: Seed RAID and Exit Criteria

Seed the RAID log with the top 5 risks (probability x impact scored 1-5, trigger, mitigation, owner), assumptions to validate, issues, dependencies. Write exit criteria: outcome metric hit, handover done, retro held. Add kill criteria: the condition under which the program stops, such as a 30-day lack of metric movement.

Key Rules

  • One page for the charter, detail in the appendix
  • Accountable is exactly one name per milestone
  • Every dependency has a provider's written confirmation or is flagged unconfirmed
  • Kill criteria are mandatory

Output Format

programs/<name>/CHARTER.md with dependency table, RACI, and RAID.md seed.

Delivery

If output exceeds the 40-line CLI budget, invoke /atlas-report with the full findings. The HTML report is the output. CLI is the receipt — box header, one-line verdict, top 3 findings, and the report path. Never dump analysis to CLI.