Use when you have little direct experience of a task but comparable work exists. Replaces inside-view guessing with the observed distribution of past similar work, then adjusts only for named differences.

License 许可
MIT
最近更新
2026-11-11
Stars
★ 80
Forks
17

01 前言 Front Matter

name
anchor-estimates-to-reference-classes
description
Use when you have little direct experience of a task but comparable work exists. Replaces inside-view guessing with the observed distribution of past similar work, then adjusts only for named differences.

02 资源文件 3

03 SKILL.md 正文

Anchor estimates to reference classes

Thinking through the steps yields an estimate that is systematically too low, because you cannot imagine the interruptions. The outside view — what actually happened on comparable work — is the better starting point. Start from the class, adjust only for differences you can name.

Procedure

  1. Name the reference class precisely: "REST endpoint added to service X by this team," not "backend work." A fuzzy class has a useless distribution.

  2. Collect at least five completed instances. Sources are usually already on disk:

    git log --merges --since="6 months ago" --pretty='%cs %s' | head -20
    
  3. If commits are noisy, use the ticket system: jira issue list -q 'project=X AND status=Done AND type=Task'. Record each item's cycle time.

  4. Compute the distribution. On small samples use the median and the 10th/90th percentiles, never the mean — one disaster skews the mean badly.

    python3 -c "d=[2,3,3,4,5,9,21]; d.sort(); print('median',d[len(d)//2],'p10',d[0],'p90',d[-1])"
    median 4 p10 2 p90 21
    
  5. Take the class median as your anchor before you look at the specific task.

  6. List concrete differences from the class median — new dependency, unfamiliar area, external reviewer. For each, move the estimate a stated amount, not "a bit": "unfamiliar library: +50%."

  7. Widen the spread too, not just the centre; a task unlike anything in the class deserves the wider interval.

  8. Record the anchor and the adjustments so the next estimate reuses the same class instead of starting cold.

Pitfalls

  • Choosing a class that flatters the estimate by including only the easy episodes; the class must be everything in the bucket, including the ones that blew up.
  • Using the mean on a five-item sample where one item ran five times the rest.
  • Adjusting by vibe after anchoring, which quietly restores the optimistic inside view you just escaped.
  • A class of one ("we shipped something like this once") dressed up as a distribution.
  • Forgetting that your own team's history is the most relevant class and is nearly always retrievable.

Verification

git log --merges --since="6 months ago" --pretty='%cs' | wc -l
# >= 5 gives you a usable class; below that, widen the interval and say the class is thin

Report the class, its instance count, median and spread, and every named adjustment with its multiplier.